A.1.01.c1.1| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,36000 | 133.700,00 | 48.132,00 |
| 2 | Tukang | L.02 | OH | 0,12000 | 181.900,00 | 21.828,00 |
| 3 | Mandor | L.04 | OH | 0,03600 | 212.600,00 | 7.653,60 |
| Jumlah Harga Tenaga Kerja | 77.613,60 | |||||
| B | Bahan | |||||
| 1 | Tanah liat / Tanah biasa/liat berpasir | M17A | M3 | 1,40000 | 67.500,00 | 94.500,00 |
| 2 | Semen / PC (kg) | M12 | Kg | 55,00000 | 1.600,00 | 88.000,00 |
| Jumlah Harga Bahan | 182.500,00 | |||||
| C | Peralatan | |||||
| Jumlah Harga Peralatan | 0,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 260.113,60 | ||||
| E | Biaya Umum dan Keuntungan (15%) x D | 15% x D | 39.017,04 | |||
| F | Harga Satuan Pekerjaan (D+E) | 299.130,64 | ||||