1.1.1.1| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,60000 | 133.700,00 | 80.220,00 |
| 2 | Tukang Kayu | L.02.03 | OH | 0,20000 | 181.900,00 | 36.380,00 |
| 3 | Tukang Batu | L.02.02 | OH | 0,20000 | 181.900,00 | 36.380,00 |
| 4 | Kepala Tukang | L.03 | OH | 0,04000 | 212.600,00 | 8.504,00 |
| 5 | Mandor | L.04 | OH | 0,01300 | 212.600,00 | 2.763,80 |
| Jumlah Harga Tenaga Kerja | 164.247,80 | |||||
| B | Bahan | |||||
| 1 | Kayu Kaso 5/7 Kelas II | M37B | m3 | 0,03870 | 3.755.000,00 | 145.318,50 |
| 2 | Kayu Papan Klas II | M46 | m3 | 0,03960 | 3.775.000,00 | 149.490,00 |
| 3 | Paku pjg 10 cm - 12 cm | MBL021 | kg | 0,58720 | 19.900,00 | 11.685,28 |
| 4 | Semen / PC (kg) | M12 | Kg | 26,40600 | 1.600,00 | 42.249,60 |
| 5 | Pasir Beton (Kasar) | M01A01 | kg | 61,56000 | 140,00 | 8.618,40 |
| 6 | Kerikil/agregat Beton | M06A01 | kg | 83,34900 | 140,00 | 11.668,86 |
| 7 | Air | M0201 | liter | 17,41500 | 199,00 | 3.465,59 |
| 8 | Residu | MBH044 | Liter | 0,40000 | 49.700,00 | 19.880,00 |
| Jumlah Harga Bahan | 392.376,23 | |||||
| C | Peralatan | |||||
| Jumlah Harga Peralatan | 0,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 556.624,03 | ||||
| E | Biaya Umum dan Keuntungan (15%) x D | 15% x D | 83.493,60 | |||
| F | Harga Satuan Pekerjaan (D+E) | 640.117,63 | ||||