1.1.1.4| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,20000 | 133.700,00 | 26.740,00 |
| 2 | Tukang Besi | L.02.04 | OH | 0,10000 | 181.900,00 | 18.190,00 |
| 3 | Tukang Batu | L.02.02 | OH | 0,10000 | 181.900,00 | 18.190,00 |
| 4 | Mandor | L.04 | OH | 0,02000 | 212.600,00 | 4.252,00 |
| Jumlah Harga Tenaga Kerja | 67.372,00 | |||||
| B | Bahan | |||||
| 1 | Seng Plat BJLS 30 | MBA015 | Lembar | 1,20000 | 96.700,00 | 116.040,00 |
| 2 | Baja L 40.40.4 | MBL050 | kg | 13,50000 | 19.500,00 | 263.250,00 |
| 3 | Kawat seng 3 mm | M71_SENG | kg | 0,30000 | 21.600,00 | 6.480,00 |
| 4 | Pasangan batu ukuran 20/50 t=40cm | MPB01 | m3 | 0,15000 | 286.500,00 | 42.975,00 |
| Jumlah Harga Bahan | 428.745,00 | |||||
| C | Peralatan | |||||
| Jumlah Harga Peralatan | 0,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 496.117,00 | ||||
| E | Biaya Umum dan Keuntungan (15%) x D | 15% x D | 74.417,55 | |||
| F | Harga Satuan Pekerjaan (D+E) | 570.534,55 | ||||