Rincian koefisien, harga komponen, konversi satuan, dan harga satuan pekerjaan.
1.1.4.1| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,12500 | 133.700,00 | 16.712,50 |
| 2 | Juru ukur | L.05 | OH | 0,25000 | 219.300,00 | 54.825,00 |
| 3 | Pembantu juru ukur | L.06 | OH | 0,25000 | 133.700,00 | 33.425,00 |
| 4 | Tenaga Ahli Pratama | L.12d | OH | 2,00000 | 900.000,00 | 1.800.000,00 |
| 5 | Tenaga Terampil Operator | L.14b | OH | 2,00000 | 145.700,00 | 291.400,00 |
| Jumlah Harga Tenaga Kerja | 2.196.362,50 | |||||
| B | Bahan | |||||
| 1 | Kayu Kaso 5/7 Cm Kelas IV | M37D | m3 | 0,15100 | 2.647.500,00 | 399.772,50 |
| 2 | Paku Payung | MBL70 | kg | 0,50800 | 35.000,00 | 17.780,00 |
| Jumlah Harga Bahan | 417.552,50 | |||||
| C | Peralatan | |||||
| 1 | Waterpass | E80 | Hari | 1,00000 | 75.000,00 | 75.000,00 |
| 2 | Theodolit | E81 | Hari | 1,00000 | 150.000,00 | 150.000,00 |
| Jumlah Harga Peralatan | 225.000,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 2.838.915,00 | ||||
| E | Biaya Umum dan Keuntungan | 15% x D | 425.837,25 | |||
| F | Harga Satuan Pekerjaan (D+E) | 3.264.752,25 | ||||