Rincian koefisien, harga komponen, konversi satuan, dan harga satuan pekerjaan.
A.2.02.5c.1| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,75000 | 133.700,00 | 100.275,00 |
| 2 | Tukang Batu | L.02.02 | OH | 0,25000 | 181.900,00 | 45.475,00 |
| 3 | Tukang Las | L.02.08 | OH | 0,15000 | 181.900,00 | 27.285,00 |
| 4 | Kepala Tukang | L.03 | OH | 0,02500 | 212.600,00 | 5.315,00 |
| 5 | Mandor | L.04 | OH | 0,07500 | 212.600,00 | 15.945,00 |
| Jumlah Harga Tenaga Kerja | 194.295,00 | |||||
| B | Bahan | |||||
| 1 | Besi Beton | M13 | Kg | 30,00000 | 14.400,00 | 432.000,00 |
| 2 | Kawat las listrik | M74 | kg | 5,40000 | 32.100,00 | 173.340,00 |
| 3 | Baja L 40.40.4 | MBL050 | kg | 4,00000 | 19.500,00 | 78.000,00 |
| Jumlah Harga Bahan | 683.340,00 | |||||
| C | Peralatan | |||||
| 1 | Las listrik 150 A (Mk); Diesel | E70 | Hari | 0,15000 | 450.000,00 | 67.500,00 |
| 2 | Bor listrik (portable) 300 Watt | E71 | Hari | 0,15000 | 30.000,00 | 4.500,00 |
| Jumlah Harga Peralatan | 72.000,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 949.635,00 | ||||
| E | Biaya Umum dan Keuntungan | 15% x D | 142.445,25 | |||
| F | Harga Satuan Pekerjaan (D+E) | 1.092.080,25 | ||||