Rincian koefisien, harga komponen, konversi satuan, dan harga satuan pekerjaan.
A.1.03.1b.2| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 1,65000 | 133.700,00 | 220.605,00 |
| 2 | Tukang Batu | L.02.02 | OH | 0,27500 | 181.900,00 | 50.022,50 |
| 3 | Kepala Tukang | L.03 | OH | 0,02750 | 212.600,00 | 5.846,50 |
| 4 | Mandor | L.04 | OH | 0,16500 | 212.600,00 | 35.079,00 |
| Jumlah Harga Tenaga Kerja | 311.553,00 | |||||
| B | Bahan | |||||
| 1 | Pasir Beton (Kasar) | M01A01 | kg | 731,00000 | 140,00 | 102.340,00 |
| 2 | Air | M0201 | liter | 202,00000 | 199,00 | 40.198,00 |
| 3 | Kerikil/agregat Beton | M06A01 | kg | 1.009,00000 | 140,00 | 141.260,00 |
| 4 | Semen / PC (kg) | M12 | Kg | 407,00000 | 1.600,00 | 651.200,00 |
| Jumlah Harga Bahan | 934.998,00 | |||||
| C | Peralatan | |||||
| Jumlah Harga Peralatan | 0,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 1.246.551,00 | ||||
| E | Biaya Umum dan Keuntungan | 15% x D | 186.982,65 | |||
| F | Harga Satuan Pekerjaan (D+E) | 1.433.533,65 | ||||