Rincian koefisien, harga komponen, konversi satuan, dan harga satuan pekerjaan.
A.1.03.2b.1| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,20000 | 133.700,00 | 26.740,00 |
| 2 | Tukang Kayu | L.02.03 | OH | 0,10000 | 181.900,00 | 18.190,00 |
| 3 | Kepala Tukang | L.03 | OH | 0,01000 | 212.600,00 | 2.126,00 |
| 4 | Mandor | L.04 | OH | 0,02000 | 212.600,00 | 4.252,00 |
| Jumlah Harga Tenaga Kerja | 51.308,00 | |||||
| B | Bahan | |||||
| 1 | Multiplek tebal 18 mm | M33D_M39C | Lembar | 0,12800 | 282.100,00 | 36.108,80 |
| 2 | Kayu Kaso 5/7 Cm Kelas IV | M37D | m3 | 0,00500 | 2.647.500,00 | 13.237,50 |
| 3 | Kayu Kaso 5/7 Cm Kelas IV | M37D | m3 | 0,00500 | 2.312.500,00 | 11.562,50 |
| 4 | Minyak bekisting | MBH051 | Liter | 0,20000 | 19.000,00 | 3.800,00 |
| 5 | Paku biasa 5 cm - 7 cm | MBL020 | kg | 0,22000 | 20.200,00 | 4.444,00 |
| Jumlah Harga Bahan | 69.152,80 | |||||
| C | Peralatan | |||||
| Jumlah Harga Peralatan | 0,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 120.460,80 | ||||
| E | Biaya Umum dan Keuntungan | 15% x D | 18.069,12 | |||
| F | Harga Satuan Pekerjaan (D+E) | 138.529,92 | ||||