Rincian koefisien, harga komponen, konversi satuan, dan harga satuan pekerjaan.
2.2.1.1.4.a| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | OH | 0,00160 | 133.700,00 | 213,92 |
| 2 | Tukang Besi | L.02.04 | OH | 0,00080 | 181.900,00 | 145,52 |
| 3 | Kepala Tukang | L.03 | OH | 0,00008 | 212.600,00 | 17,01 |
| 4 | Mandor | L.04 | OH | 0,00016 | 212.600,00 | 34,02 |
| Jumlah Harga Tenaga Kerja | 410,46 | |||||
| B | Bahan | |||||
| 1 | Besi Beton | M13 | Kg | 1,05000 | 14.400,00 | 15.120,00 |
| 2 | Kawat Beton / Bendrat | M14 | Kg | 0,02800 | 19.900,00 | 557,20 |
| Jumlah Harga Bahan | 15.677,20 | |||||
| C | Peralatan | |||||
| 1 | Cutter baja beton | E60 | Hari | 0,00040 | 250.000,00 | 100,00 |
| 2 | Bender baja beton | E61 | Hari | 0,00040 | 250.000,00 | 100,00 |
| Jumlah Harga Peralatan | 200,00 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 16.287,66 | ||||
| E | Biaya Umum dan Keuntungan | 15% x D | 2.443,15 | |||
| F | Harga Satuan Pekerjaan (D+E) | 18.730,81 | ||||