Rincian koefisien, harga komponen, konversi satuan, dan harga satuan pekerjaan.
A.3.05.2c.2.d| No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan (Rp) |
Jumlah Harga (Rp) |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| A | Tenaga Kerja | |||||
| 1 | Pekerja | L.01 | Jam | 0,09400 | 19.100,00 | 1.795,40 |
| 2 | Tukang | L.02 | Jam | 0,04700 | 25.985,71 | 1.221,33 |
| 3 | Mandor | L.04 | Jam | 0,00940 | 30.371,43 | 285,49 |
| Jumlah Harga Tenaga Kerja | 3.302,22 | |||||
| B | Bahan | |||||
| 1 | Steel Sheet Pile Type III (400 x 125 x 13,0 mm) | MBL061 | m1 | 1,00000 | 1.054.200,00 | 1.054.200,00 |
| Jumlah Harga Bahan | 1.054.200,00 | |||||
| C | Peralatan | |||||
| 1 | Pile Vibratory Driver - 80 HP (Electric) | E.37.b | Jam | 0,04700 | 55.000,00 | 2.585,00 |
| 2 | Truck Crane 25 Ton | E52 | Jam | 0,04700 | 1.581.750,00 | 74.342,25 |
| Jumlah Harga Peralatan | 76.927,25 | |||||
| D | Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) | 1.134.429,47 | ||||
| E | Biaya Umum dan Keuntungan | 15% x D | 170.164,42 | |||
| F | Harga Satuan Pekerjaan (D+E) | 1.304.593,89 | ||||