| No. | Kode | Kelompok | Uraian | Rumus | Satuan | Volume |
|---|---|---|---|---|---|---|
| 1 | QT-A1 | Pekerjaan Tanah | Galian tanah bangunan utama | ((P x L) - (Pwet x Lwet)) x Hgali | m3 | 115,80 |
| 2 | QT-A2 | Pekerjaan Tanah | Galian wet well / sump pit | Pwet x Lwet x Hwet | m3 | 285,91 |
| 3 | QT-A4 | Pekerjaan Tanah | Urugan pasir bawah bangunan | P x L x t_urugan_pasir | m3 | 25,65 |
| 4 | QT-B1 | Struktur Bawah | Lantai kerja | P x L x t_lantai_kerja | m3 | 12,83 |
| 5 | QT-B2 | Struktur Bawah | Slab lantai utama | ((P x L) - (Pwet x Lwet)) x t_slab_lantai | m3 | 38,60 |
| 6 | QT-B4 | Struktur Bawah | Slab dasar wet well | Pwet x Lwet x t_slab_wet_well | m3 | 25,41 |
| 7 | QT-B5 | Struktur Bawah | Dinding beton wet well | Kelilingwet x Hwet x t_dinding_wet_well | m3 | 52,33 |
| 8 | QT-B6 | Struktur Bawah | Pedestal pompa | n x Pped x Lped x Tped | m3 | 7,20 |
| 9 | QT-B7 | Struktur Bawah | Pedestal panel | n x Ppanel x Lpanel x Tpanel | m3 | 0,48 |
| 10 | QT-C1 | Struktur Atas | Kolom beton | n_kolom x b_kolom x h_kolom x tinggi_kolom | m3 | 10,56 |
| 11 | QT-C2 | Struktur Atas | Balok beton | b_balok x h_balok x panjang_total_balok | m3 | 17,45 |
| 12 | QT-D1 | Tulangan | Tulangan slab lantai utama | V_slab x rasio_slab | kg | 4.246,00 |
| 13 | QT-D3 | Tulangan | Tulangan wet well | (V_slab_wet + V_dinding_wet) x rasio_wet | kg | 11.661,00 |
| 14 | QT-D4 | Tulangan | Tulangan kolom | V_kolom x rasio_kolom | kg | 1.900,80 |
| 15 | QT-D5 | Tulangan | Tulangan balok | V_balok x rasio_balok | kg | 2.966,50 |
| 16 | QT-D7 | Tulangan | Tulangan pedestal | V_pedestal x rasio_pedestal | kg | 1.075,20 |
| 17 | QT-E2 | Bekisting | Bekisting dinding wet well | Kelilingwet x Hwet x 2 | m2 | 348,84 |
| 18 | QT-E3 | Bekisting | Bekisting kolom | n x 2 x (b+h) x tinggi | m2 | 105,60 |
| 19 | QT-E4 | Bekisting | Bekisting balok | Lbalok x ((2xh)+b) | m2 | 151,22 |
| 20 | QT-E6 | Bekisting | Bekisting pedestal pompa | n x 2 x (P+L) x T | m2 | 21,60 |
| 21 | QT-E7 | Bekisting | Bekisting pedestal panel | n x 2 x (P+L) x T | m2 | 1,52 |
| 22 | QT-F1 | Arsitektur | Pasangan dinding non-struktur | Luas dinding bersih | m2 | 369,18 |
| 23 | QT-F2 | Arsitektur | Plesteran dinding dua sisi | 2 x luas_dinding_bersih | m2 | 738,36 |
| 24 | QT-F3 | Arsitektur | Acian dinding dua sisi | 2 x luas_dinding_bersih | m2 | 738,36 |
| 25 | QT-F6 | Arsitektur | Finishing lantai | Luas bangunan - luas wet well | m2 | 193,00 |
| 26 | QT-F7 | Arsitektur | Waterproofing area basah | Luas wet well | m2 | 63,54 |
| 27 | QT-G2 | Atap | Penutup atap ringan | Luas bangunan x faktor kemiringan | m2 | 282,19 |
| 28 | QT-I1 | Pekerjaan Luar | Drainase keliling | Keliling x b_drainase x h_drainase | m3 | 11,32 |
| 29 | QT-I3 | Pekerjaan Luar | Paving / perkerasan area kerja | Luas paving input | m2 | 120,00 |